This baby has 1716 square feet of floor. Yes its 108 sq. ft larger than the main house. Just a little history: Concrete poured in Nov/Dec of 2003. Started framing on January 5th. Decking the trusses started on Feb 5th. We are in high hopes of getting an inspection by Monday that will allow us to put the roof on to protect the structure. Things are moving very fast around here. As you can tell by the pictures below. Back to work we go!!! Enjoy the new pictures.
Rough framing back on January 15th.
Roofing the main section of the garage. Feb 8th.
Justen decked this area by himself! Dad is very proud of him. Feb 9th.
Roofing on the North side with primer painted on the siding.
Viewing the South end of the garage.
The Artist (aka Justen) applying primer at 9pm. Just had to get the last two gallons on before he quits for the night.